Understanding where the heat goes in the anode baking hall of an aluminium plant, to tackle summer overheating, protect technical equipment and improve air quality in the working areas.
Published on · By the CFD engineers of EOLIOS Engineering
In an aluminium smelter, that is, a plant producing primary aluminium, the hall where the anodes are baked never stops. The furnaces continuously release a considerable amount of heat, which the building removes solely by natural ventilation: air enters through the façades, warms up in contact with the process, rises, then escapes through the roof. As long as this balance holds, the hall breathes. When production intensifies and summer sets in, it breaks down.
The operator asked EOLIOS to carry out a thermo-aeraulic study to answer a question that is simple to ask and hard to settle without the right tools: where does the heat build up, why, and which changes to the building would really get it out? Three things are at stake: operator comfort, air quality in the working areas and the protection of the technical equipment that travels and parks in the upper part of the hall, exactly where the air is hottest.
We carried out the study in two stages. First an on-site audit, in full production, to observe how the air really moves. Then a CFD numerical simulation of the whole hall, calibrated on these observations, to replay a summer day and compare, before any works, several ways of upgrading the ventilation.
Key points. An anode baking hall is naturally ventilated by its own heat. When the air inlets in the façades and the outlets in the roof can no longer keep pace with the process, a layer of hot air settles under the roof, at the height of the overhead cranes and service machines, and the air stagnates in some areas. The on-site audit followed by the CFD simulation made it possible to see this layer, explain where it comes from and compare several modifications. The result: a prioritised roadmap that separates the actions that really work from those that merely shift the problem.
An aluminium smelter is a plant that produces primary aluminium by electrolysis. Aluminium is not melted out of its ore, it is extracted from it. Alumina is dissolved in a molten bath, then broken down by a very high electric current: this is electrolysis. In each cell, the current arrives through large carbon blocks, the anodes, which are consumed as the reaction proceeds and have to be replaced regularly. Alongside its metal, a smelter therefore manufactures an uninterrupted stream of new anodes.
Before it reaches a cell, each anode has to be baked for a long time, at very high temperature, to acquire its mechanical strength and conductivity. That is the role of the baking hall, the subject of this study: a very long building, extended by a warehouse where the baked anodes finish cooling before leaving for the electrolysis cells.

The furnace occupies the floor of the hall over almost its entire length. It is made up of a series of pits, separated by hollow walls of refractory brick. The anodes are placed in them, then covered with a fine granular material, the packing coke, which protects them and contains the heat. What makes the process distinctive can be said in one sentence: it is not the anodes that move towards the heat, it is the fire that moves. Several mobile fires advance at the same time along the furnace, section after section, day and night.
At any moment, the hall therefore houses every stage of the cycle side by side:
For the air in the hall, this means multiple heat sources of very different intensities, which change position over the days. Added to these are the anodes fresh out of the furnace, still very hot, which cross the building on their way to the warehouse.

A baking furnace in which the products stay still while the heating zone moves from section to section. The heat from the cooling sections is used to preheat those that are waiting: the process is continuous and frugal, but it turns the whole hall into a permanent heat source.
The hall has no fans to renew its air. It works by stack effect: the air warmed by the furnaces, being lighter, rises to the static roof ventilators, and as it leaves it draws in outside air through the louvres in the façades and the low-level openings. The hotter the process, the harder the building draws. The principle is robust, free and cannot break down. It does, however, require the air inlets and outlets to remain in proportion to the heat to be removed.
Louvres are slatted openings, set in the façades, that let air in while keeping the rain out. Static roof ventilators are fixed openings in the roof through which hot air escapes without any fan. Together, they form the inlet and the outlet of the natural ventilation of an industrial hall.
But the hall has changed. Production capacity has increased and the baking cycles have intensified: the building itself has stayed the same. Some of its openings have even lost efficiency over time. Some low-level louvres now let through only a small share of the intended airflow, others are closed, and on several bays the original louvres have given way to glazed light panels, which bring in daylight but not a breath of air.
In winter and mid-season, the incoming air is cool and the system absorbs these shortfalls. In summer, the fresh air arrives already hot. The whole air column of the hall shifts up the temperature scale, and the heat that cannot find the way out fast enough builds up under the roof. This is stratification: bearable air at floor level, an overheated layer several storeys higher.
The superposition of layers of air at different temperatures in a large volume. Hot air, being lighter, gathers under the roof. If extraction is insufficient, this layer thickens and gradually moves down towards the occupied areas.
This hot layer does not float in a vacuum. It is at this height that the overhead cranes and service machines that load and unload the furnace travel, equipment that production cannot do without. It is also where their parking and maintenance areas are located. Like all electrical and automated equipment, they cope poorly with a lastingly overheated atmosphere, and the teams that maintain them work in the hottest air in the building. Protecting these technical systems and those who look after them is one of the concrete objectives of the study.

Baking anodes does not only release heat. It also produces effluents: fumes from the baking itself and carbon-based fine dust linked to the handling of the packing coke. In a naturally ventilated hall, the same air carries away both the heat and these pollutants. Where it circulates well, both are removed together through the roof. Where it stagnates, both build up.
This kinship has a practical consequence: overheating cannot be treated without looking at the path the air follows. An opening that cools an area by drawing in air that has passed over the furnaces can degrade the air quality there. The study therefore keeps two questions in view at all times: where does the heat go, and where has the air come from when it reaches each working area? That is the whole point of analysing pollutant dispersion with the same tools as the thermal behaviour.
Before modelling, you have to look. Our engineers examined the hall in detail in full production, without disturbing the teams, using three complementary families of tools:
The weather conditions on the day were recorded in parallel, because wind has a direct bearing on the behaviour of a naturally ventilated building. Finally, the audit was used to check the geometry of the hall, the real state of each opening and the layout of the equipment.
The hall is indeed set in motion by its furnaces: above the hot zones, the air rises strongly towards the roof, with an overall drift along the building. But this driving force is not enough to renew the air everywhere. The audit revealed four weaknesses:
The warehouse, for its part, behaves like a buffer volume: little heat, little draught, slow air. These findings are valuable, but they remain snapshots, taken at a few points on a given day. To quantify, explain and above all test remedies, calculation was needed.
Measurement describes a few points. CFD simulation (computational fluid dynamics) reconstructs the entire volume: the velocity, direction and temperature of the air at every point in the hall, including under the roof, where nobody can hold an anemometer. Above all, it offers what no measurement campaign can: modifying the building virtually, opening a façade, adding a louvre, and watching how the hall responds without touching production.
The baking hall and the warehouse were rebuilt in three dimensions, with their structure, façades, openings and equipment. The furnace is not treated as a uniform hot block: it is divided according to the phases of the cycle, and each portion is given the temperatures recorded during the audit, those of the packing coke, the walls, the openings through which the hot gases flow, and the blowing and exhaust devices. The anodes in transit, those cooling in the warehouse and the masonry beneath the furnace are also represented as heat sources.
Two modelling choices give the result its value:

The first simulation is not looking for anything new. It replays the day of the audit: same weather (13 °C outside, a 27 km/h wind), same openings, same fire position. We then compared the calculation with the smoke tests, the measured velocities and the field observations. The main air movements, the main inlets, the stagnation zones and the stratification under the roof are all found in the model. This calibration step is essential: it is what then allows the model to be trusted in situations that nobody has been able to measure.
Key takeaway. A numerical model is only worth something if it matches the field. By calibrating the simulation on the audit before studying any scenario, we make sure that the “before and after” comparisons describe the real hall, not a theoretical building.
With the model validated, we placed it in the conditions that cause the problem: a summer day at 35 °C, with the building in its current state. This reference simulation serves as a baseline, the one against which all the solutions are then compared.
First lesson: the overall pattern of the airflows does not change with the season; it is still dictated by the furnaces and the openings. What changes is the temperature level. In summer, the hot air forms a continuous layer under the roof, fed by the plumes from the furnaces, which extends over a large part of the hall and reaches the height of the service machines. The static roof ventilators can no longer remove the heat as fast as the process produces it.

Above each fire, the hot air rises in a plume, exactly as expected. The problem lies at the top. The shallow roof pitch does not naturally lead the hot air to the ventilators: between two ventilators it spreads out, slows down and forms pockets. It is in these gaps, in the centre of the hall, that the simulation finds the highest temperatures.



Second lesson: not all bays are equal. Where both façades have louvres, fresh air penetrates to the heart of the hall and the sweep is adequate. Where one façade has a glazed light panel, the supply becomes asymmetrical and a recirculation loop settles in the upper part. Where two glazed light panels face each other, almost no air comes in: this is the most unfavourable configuration in the building. Lastly, the ends of the hall remain outside the general movement. In all these areas, the air turns on itself instead of leaving, and holds back the heat and the effluents with it.

At head height, the picture is more nuanced. The streams of cool air from the louvres and doors keep the aisles at a temperature close to that outside. Comfort at floor level therefore depends directly on being close to a working air inlet: one more reason to look at the state of the openings. The warehouse, with less heat and fewer roof openings, remains a calm, poorly renewed volume, on which changes to the baking hall will have little effect.


Once the diagnosis has been made, the simulation changes role: it becomes a test bench. Same summer day, same wind, same production; only the building changes. Each option, defined with the operator, can thus be compared with the current state, all other things being equal, which no real-life trial would allow.
The first idea is the simplest: give the low-level louvres back their full capacity and reopen those at the far end of the hall. Fresh air enters more easily and penetrates further, and the hot layer under the roof recedes slightly. The simulation holds a first surprise: with the prevailing wind, the louvres at the far end do not let air in, they let it out. They usefully relieve that end of the hall, but not in the way one imagined. The gain remains moderate and the overall behaviour of the hall is not transformed.
The second option adds to the first the replacement of the glazed light panels with louvres, which amounts to returning to the configuration planned when the building was designed. This time, the change is visible. Fresh air enters along the whole length of the hall, the recirculation zones shrink markedly and the plumes rise more directly towards the ventilators. The hot layer is no longer continuous: it breaks up into smaller volumes, located above the fires. A stagnation zone nevertheless persists at the far end of the hall, which the geometry of the building makes difficult to clear through the façades alone.

The third option responds directly to the equipment issue: creating new high-level louvres, on both sides of the hall, at the parking and maintenance areas of the service machines. Thermally, the benefit is clear: the heat trapped under the roof finds new ways out, and the upper part of the hall cools down noticeably.
But the simulation does not stop at temperatures. The analysis of the pressures shows that these openings do not all behave in the same way. On the windward façade, at the start of the hall, they let fresh air in: this is the ideal behaviour for a maintenance area. On the opposite façade and at the end of the hall, they work as exhausts. And the streamlines then reveal what no temperature map hinted at: the air leaving through the louvres at the far end has crossed a large part of the building, above the baking zones. By cooling this maintenance area, we therefore draw in air that may be laden with effluents.
Key takeaway. An opening is not an air inlet by decree. Depending on the wind and the pressure balance in the building, it admits fresh air or releases hot air. Without simulation, this difference is only discovered once the works are finished.
Four sections of the same hall, for the same summer day and the same wind: only the building changes.
Heat: continuous hot layer under the roof, at the height of the service machines.
Air: few inlets, stagnation zones at the ends and along the façades.
Heat: the layer recedes slightly.
Air: fresh air penetrates better at low level, but the overall behaviour does not change.
Heat: fragmented layer, confined above the fires.
Air: fresh air distributed along the whole length of the hall. Stagnation persists at the far end of the building.
Heat: upper part markedly cooler.
Air: at the end of the hall, the extracted air has first passed over the furnaces: to be combined with reinforced roof extraction.
Hot air built up under the roofIncoming fresh airHot air removedStagnant air
Schematic diagrams based on the simulations. Qualitative reading, not to scale.
The final diagnosis can be summed up in one sentence: the hall lacks both air inlets and roof extraction capacity. Acting on only one of the two is not enough. From there, the study does not deliver a single solution but a prioritised roadmap, in which each action is linked to the effect the simulation attributes to it:
Restore the air inlets. Refurbish the low-level louvres and replace the glazed light panels with louvres: this is the foundation, without which no other action delivers its full benefit.
Reinforce roof extraction. Add static roof ventilators above the areas concerned, so that the heat and the effluents leave from the top, as close as possible to their source, before reaching the maintenance areas.
Bring fresh air in near the service machines. With a roof that draws harder, the high-level louvres work as inlets: the equipment and the maintenance teams receive cool air rather than furnace air.
Extend the openings to the far end of the building. Beyond the end of the furnaces, to deal with the last area where the air still stagnates.
Plan a fallback solution. If the roof cannot be modified, localised mechanical extraction at the end of the hall, switched on only during maintenance periods, is a lighter alternative, to be sized by a dedicated study.
The operator thus has what is most often missing when a budget is about to be committed: a clear view of what each action delivers, the order in which to carry them out, and the false good ideas to avoid. Opening high-level louvres at the end of the hall without reinforcing the roof, for example, would have cooled the area while degrading its air: the simulation made it possible to see this before building it.
In a hot-process hall, ventilation cannot be decreed, it has to be understood. A building of this size, ventilated by its own heat and exposed to the wind, rarely reacts as intuition suggests. Our job is to make this behaviour visible, explainable and predictable.
Do you operate a hall subject to high heat loads, a foundry, a glassworks, a steelworks, an aluminium smelter? Our engineers can diagnose your ventilation and use simulation to check the effect of each modification before works.
Summer overheating, natural ventilation and CFD simulation in an anode baking hall.
The furnaces release heat continuously and the building removes it by natural ventilation alone. In summer, the incoming air is already hot (35 °C in the scenario studied): the whole air column shifts upwards and a layer of overheated air settles under the roof if the air inlets or the roof outlets can no longer keep pace with the process.
Yes, provided it stays balanced. It works without energy and without breakdowns, but it needs sufficient air inlets in the façades and well-placed outlets in the roof. When production increases or openings are blocked off, that balance is lost and has to be rebuilt, sometimes with localised mechanical support.
Measurements describe a few points on a given day. Simulation reconstructs the entire volume of the hall, including under the roof where nothing can be measured, and makes it possible to test changes to the building before any works begin. The two complement each other: the audit is used to calibrate the model, and the model is used to compare solutions.
No. Depending on its exposure to the wind and its position relative to the building's neutral pressure plane, the same opening can let fresh air in or let hot air out. Badly placed, it can even carry pollutants towards an occupied area. This is precisely what simulation makes it possible to check before investing.
Yes. The audit takes place under normal operating conditions, without disturbing the teams, and all the solutions are then tested on the numerical model. The operator only launches works once the gains of each option have been compared.
Explore our expertise, projects and technical papers to go further than the FAQ.
In under three minutes, the video flies over the 3D model of the site, then enters the hall: the temperatures at furnace level and in section, the hot air volumes rising from the baking equipment, and the streamlines that follow the air up to the roof.